The following is a schedule of construction activity at Hunter Hall (222 East 16th Street) from Sept. 19 - Oct. 1. Please feel free to contact us at projects@friendsseminary.org or call our Information Line at 646-979-5225 for questions or comments. WORK HOURS
Monday through Friday: 7am – 6pm
Saturday: 9am – 3pm, only as needed
No work on Sundays throughout construction (except in an emergency)
As weather conditions and unforeseen circumstances may influence the progress of the work, all dates and times mentioned may be subject to change.
INTERIOR WORK
Gym through Fourth Floor: Finalizing reconstruction of interiors (painting, finishes, etc.).
New construction (fifth and sixth floors): Layout; installation of metal studs; installation of mechanicals, plumbing, electrical, etc.
EXTERIOR WORK
Continued installation of bricks and concrete masonry units (CMUs) and windows on both north and south facades.
Continued waterproofing and fireproofing at columns.
Begin installation of CMUs and brick for new construction (fifth and sixth floors).
Installtion of dens-glass for exterior walls of fifth and sixth floors.
Preparation and installation of roofing for new top floor; also installation of roof on stair bulkheads.