 The redevelopment was designed by Kliment Halsband Architects. The construction manager is Tishman Construction. 

Please feel free to contact us at projects@friendsseminary.org or call our Information Line at 646-979-5225 for questions or comments.


 

Construction Activities for April 24 - May 31

April 24, 2017

 

The following is a schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) and a portion of Hunter Hall (222 East 15th Street) for April 24 through May 31.

 

For more information about the Townhouse construction or the activities outlined below, feel free to review the slide presentation which the school shared with neighbors at our previous community construction meeting last month. As always, please do not hesitate to contact us at projects@friendsseminary.org or call our Information Line at (646) 979-5225 with questions or comments.  

 

TOWNHOUSES

 

INTERIOR WORK

  • Installation of temporary light and power

  • Selective demolition of interior walls

  • Selective demolition of floor slab required for temporary steel supports

  • Selective removal of interior fixtures and finishes

  • Limited asbestos abatement

  • Structural surveying

 

EXTERIOR WORK

  • Installation of protective scaffolding and sidewalk shed

  • Installation of site perimeter safety fencing

  • Selective demolition of rooftop mechanicals

  • Tree removals  

  • Structural surveying

 

HUNTER HALL

 

EXTERIOR WORK

  • Installation of play roof screen and netting

 

 

 

 

 

 

 

 

 

 