Construction Activities for Oct. 1 - Nov. 5

October 3, 2018

The following is a detailed schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) for Oct 1 through Nov. 5.


 

EXTERIOR WORK ACTIVITIES ON THE TOWNHOUSES

 

·       Repointing of the Townhouse façade

·       Installing new window sills

·       Terracotta repair and replacement

·       Parapet flashing and railing at terrace

·       Hand erect remaining structural steel

·       Install remaining metal decks and pour stops

·       Pour concrete for remaining slab infills

·       Pour roof curbs and apply roofing

·       Construct new cornice

·       Construct exterior stud and brick walls

·       Gallery roof installation

·       Bring in new gas, water and sewer services

·       Rigging HVAC Equipment

 

INTERIOR WORK ACTIVITIES ON THE TOWNHOUSES

·      Plumbing risers and roughing

·      HVAC risers and roughing

·      Ductwork risers and branch work

·      Electrical risers and roughing

·      Fire Protection risers and roughing

·      Install stair handrails

·      Begin elevator construction

·      Bring on live electrical power

·      Temp lighting and power on decks

 