top of page

Construction Activities for Oct. 1 - Nov. 5

The following is a detailed schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) for Oct 1 through Nov. 5.

EXTERIOR WORK ACTIVITIES ON THE TOWNHOUSES

· Repointing of the Townhouse façade

· Installing new window sills

· Terracotta repair and replacement

· Parapet flashing and railing at terrace

· Hand erect remaining structural steel

· Install remaining metal decks and pour stops

· Pour concrete for remaining slab infills

· Pour roof curbs and apply roofing

· Construct new cornice

· Construct exterior stud and brick walls

· Gallery roof installation

· Bring in new gas, water and sewer services

· Rigging HVAC Equipment

INTERIOR WORK ACTIVITIES ON THE TOWNHOUSES

· Plumbing risers and roughing

· HVAC risers and roughing

· Ductwork risers and branch work

· Electrical risers and roughing

· Fire Protection risers and roughing

· Install stair handrails

· Begin elevator construction

· Bring on live electrical power

· Temp lighting and power on decks

Should you have questions or concerns regarding the construction project, please don't hesitate to contact us by email at projects@friendsseminary.org or by phone at (646) 979-5225.


bottom of page