Construction Activities for April 2 - May 31

April 2, 2019

The following is a detailed schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) between April 2 and May 31, 2019:

 

  • Construction work hours will remain the same: 7 AM – 6 PM on Monday – Friday, and 9 AM – 5 PM on Saturday

 

April:

  • South elevation standing seam metal

  • South elevation operable window glass installation with scaffold removal

  • Townhouse roof pavers and acoustical metal enclosures

  • North elevation brick restoration on Hunter Hall

  • Removal of scaffolding and overhead protection in front of Hunter Hall only 

  • Installation of the Great Room east curtain wall glass and removal of weather walls/courtyard scaffolding

  • Interior finishes and starting to paint

  • Gas and water connections on 16th Street by ConEd and our contractors

  • Exploratory 15th Street excavation for DEP in relation to capped water service 

 

May:

  • Removal of north elevation scaffold and alteration to overhead protection and lane closures. Please note we will be setting up a pedestrian walkway in the street in front of the Townhouses in order to begin the front yard work

  • Third floor Peace Terrace waterproofing and pavers

  • Third floor Peace Terrace planters and east guard rail installation

  • Third floor Peace Terrace NanaWall system door installation

  • Interior finishes and painting

 

Should you have questions or concerns regarding the construction project, please don't hesitate to contact us by email at projects@friendsseminary.org or by phone at (646) 979-5225.