The following is a detailed schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) between June 2 and July 31, 2019:
Construction work hours will remain the same: 7 AM – 6 PM on Monday – Friday, and 9 AM – 5 PM on Saturday
June:
Interior finishes and painting continues
Third floor Peace Terrace pavers and railing
Interior stair demolition continues
MEP work
Greenhouse delivery and installation
Supplemental steel for infill floor plates at interior stair “W”
Interior reconstruction at wall and ceiling of stair “W”
Interior lighting installation and painting
Front yard reconstruction
Courtyard reconstruction
Reconstruction of interior spaces continues
July:
Third floor Peace Terrace planters and east guard rail installation
Interior finishes and painting
Ceiling tile white-out
Lobby flooring
Interior assembly room flooring and railing
Millwork and wall paneling continuing
Seating delivery and installation
Touch-up painting