The following is a detailed schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) between August 15 - September 30:
Construction work hours will remain the same: 7 AM – 6 PM on Monday – Friday, and 9 AM – 5 PM on Saturday
August:
Townhouse facade touch up
Townhouse facade balconette installation
Townhouse facade front fence and gate completion
Interior finishes and painting touch up continues
Begin greenhouse erection
Hardware fine tuning
Great Room floor finishing
Great Room AV installation
Front yard planting
Install permanent elevator doors
Courtyard restoration
Millwork installation continues
MEP Commissioning
September:
Greenhouse and MEPS installation completion
Millwork completion
Stair W modifications
Close out and De-mobilization