The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning August 22 and ending September 9.
Plumbing
Sprinkler standpipe relocation
Roof
Remove standing seam panels
Install insulation
Waterproofing
Electrical
Electrical roughing in new framing
Carpentry
Stair expansion framing
Concrete
Install forms and slabs for stair expansion