Construction Activities for December 5 – December 30, 2022

Following is a schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning December 5 and ending December 30.

Please note that there will be no work on Monday, December 26 and Monday, January 2, 2023.

Roofing

  • Waterproofing

  • Install interior insulation and wall panels

Electrical

  • Electrical roughing

Carpentry

  • Install doors and frames

Millwork

  • Finish carpentry

HVAC

  • Install louvers and ductwork

Fiberglass

  • Install wall panels and dome

  • Plasterwork