Following is a schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning December 5 and ending December 30.
Please note that there will be no work on Monday, December 26 and Monday, January 2, 2023.
Roofing
Waterproofing
Install interior insulation and wall panels
Electrical
Electrical roughing
Carpentry
Install doors and frames
Millwork
Finish carpentry
HVAC
Install louvers and ductwork
Fiberglass
Install wall panels and dome
Plasterwork