Construction Activities for October 10 – October 21, 2022

The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning October 10 and ending October 21.

Plumbing

  • Sprinkler riser relocation

  • Install standpipe

Roof

  • Waterproofing

Electrical

  • Electrical roughing

  • Install fire alarm

Carpentry

  • Framing

  • Install insulation

Concrete

  • Install curbs

Steel

  • Installations

  • 3rd-party inspections

HVAC

  • Install dampers and louvers

  • Install radiator

Fireproofing

  • Spray on fireproofing

  • 3rd-party inspections