The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning October 10 and ending October 21.
Plumbing
Sprinkler riser relocation
Install standpipe
Roof
Waterproofing
Electrical
Electrical roughing
Install fire alarm
Carpentry
Framing
Install insulation
Concrete
Install curbs
Steel
Installations
3rd-party inspections
HVAC
Install dampers and louvers
Install radiator
Fireproofing
Spray on fireproofing
3rd-party inspections