Construction Activities for September 12 - 23, 2022

The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning September 12 and ending September 23.

Plumbing

  • Sprinkler riser relocation and standpipe installation

Roof

  • Insulation and vapor barrier work

  • Waterproofing

Electrical

  • Electrical roughing

Carpentry

  • Framing

  • Insulation

Demolition

  • Opening to below stairwell (hand tools only)

Concrete

  • Install forms and slabs for stair expansion

Steel

  • Steel rigging and installation


Please note that on Saturday, September 17, structural steel will be erected on to the rooftop for installation. This will require 1-day street closure of 16th Street to allow for the mobile hydraulic crane to lift the steel. Flag persons will be present during the operation to ensure pedestrian safety. The School will place notices on 16th Street prior to commencement of this operation.

Comments


Receive Updates Via Email

Join our project mailing list to receive regular updates.

Success! Thanks for joining our mailing list!

BUILDING REDEVELOPMENT

Design: Kliment Halsband Architects

Construction: Tishman Construction

SKYSPACE

Design: James Turrell

Site Assembly and Installation: Taurino Management
 

QUESTIONS/COMMENTS
Contact us at projects@friendsseminary.org.

© Friends Seminary 2022, All Rights Reserved

bottom of page