The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning September 12 and ending September 23.
Plumbing
Sprinkler riser relocation and standpipe installation
Roof
Insulation and vapor barrier work
Waterproofing
Electrical
Electrical roughing
Carpentry
Framing
Insulation
Demolition
Opening to below stairwell (hand tools only)
Concrete
Install forms and slabs for stair expansion
Steel
Steel rigging and installation
Please note that on Saturday, September 17, structural steel will be erected on to the rooftop for installation. This will require 1-day street closure of 16th Street to allow for the mobile hydraulic crane to lift the steel. Flag persons will be present during the operation to ensure pedestrian safety. The School will place notices on 16th Street prior to commencement of this operation.