Construction Activities for September 26 – October 7, 2022

The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning September 26 and ending October 7.

Plumbing

  • Sprinkler riser relocation

  • Install standpipe

Roof

  • Waterproofing

Electrical

  • Electrical roughing

Carpentry

  • Framing

  • Insulation

Concrete

  • Install curbs

Steel

  • Installations

  • 3rd-party inspections

HVAC

  • Install dampers and louvers

Fireproofing

  • Spray on fireproofing

  • 3rd-party inspections