Construction Activities for June 2 - July 31

June 1, 2019

The following is a detailed schedule of construction activity on the Townhouse buildings (212-216 East 16th Street) between June 2 and July 31, 2019:

 

  • Construction work hours will remain the same: 7 AM – 6 PM on Monday – Friday, and 9 AM – 5 PM on Saturday

June:

  • Interior finishes and painting continues

  • Third floor Peace Terrace pavers and railing

  • Interior stair demolition continues

  • MEP work

  • Greenhouse delivery and installation

  • Supplemental steel for infill floor plates at interior stair “W”

  • Interior reconstruction at wall and ceiling of stair “W”

  • Interior lighting installation and painting

  • Front yard reconstruction

  • Courtyard reconstruction 

  • Reconstruction of interior spaces continues

 

July:

  • Third floor Peace Terrace planters and east guard rail installation

  • Interior finishes and painting

  • Ceiling tile white-out

  • Lobby flooring

  • Interior assembly room flooring and railing

  • Millwork and wall paneling continuing

  • Seating delivery and installation

  • Touch-up painting