Construction Activities for November 11 – November 25, 2022

The following is a detailed schedule of construction activities on the James Turrell Skyspace (218 East 16th Street roof) for the period beginning November 11 and ending November 25.


Please note that there will be no work on Friday, November 25.

Plumbing

  • Install sprinkler branches

Roof

  • Waterproofing

  • Install interior insulation and wall panels

Electrical

  • Electrical roughing

Carpentry

  • Framing

  • Install interior insulation

  • Third-party inspections

Millwork

  • Install interior bench bases

HVAC

  • Install louvers and ductwork

Fiberglass

  • Install wall panels and dome

Comments


Receive Updates Via Email

Join our project mailing list to receive regular updates.

Success! Thanks for joining our mailing list!

BUILDING REDEVELOPMENT

Design: Kliment Halsband Architects

Construction: Tishman Construction

SKYSPACE

Design: James Turrell

Site Assembly and Installation: Taurino Management
 

QUESTIONS/COMMENTS
Contact us at projects@friendsseminary.org.

© Friends Seminary 2022, All Rights Reserved

bottom of page